2020 Update #8
First Look at the Tunnel, Ode to Harriet The Highlights Fabrication of tunnel reaches mid-point Winter work continues Just southeast of...


2020 Update #7
Winter Work, WinterFest, Winter Reading The Highlights Status quo on the work front Celebrate WinterFest on Sunday First things first: ...


2020 Update #6
Winter Challenges The Highlights Winter Weather Deteriorating Pavement on Main Street Bridge The first week of February was a short week...


2020 Update #5
Amtrak Rail Platform Update, Closing Out January The Highlights Public information meeting on the Amtrak Rail Platform Winter work update...


2020 Update #4
Winter Work, Summer Parking The Highlights Downtown parking during summer construction Preparations underway at Fifield Farm Last week we...


2020 Update #3
The Challenges of Winter Work, Introducing The Shuttlebury Highlights A quiet week in the rail corridor A downtown shuttle to help with...


2020 Update #2
Winter Work Continues, Looking Ahead to Summer Highlights Key dates for your 2020 calendar Maine wraps up, ECI ramps up Now that 2020 has...


2020 Update #1
Back To Work The Highlights Maine D&B working this weekend Running down the winter work schedule I hope you thoroughly enjoyed your time...


2019 Update #46
Silent Night(s) Highlights No construction Christmas Eve through New Year's Day Celebrating our volunteers For the first time since early...


2019 Update #45
Santa Comes to Town, The Final Blast The Highlights Four blasting weekends come to end No construction Christmas Eve through New Year’s...