Temporary Bridges Update #9
- Jim Gish, Community Liaison
- Jun 13, 2017
- 1 min read
Mid-Day Update
The planned shutoff of the waterline on Main Street will likely take place Wednesday afternoon at 2 PM. If prep work takes longer than expected, the shutoff will occur Thursday at 2 PM.
Buildings affected are those on the north (Post Office) side of Main Street from the Battell Bridge up to the Community House, plus St. Stephen’s
Water will be off from 2 PM through the rest of the afternoon.
I will have more info in the Wednesday morning update.